CONSTRUCTION UPDATES

construction Progress

Web Designer 31%
*According to our internal inspection conducted on 31-08-2025, the overall project's progress is 31%.

31-08-2025

VIEWZ 1

  1. Ground Floor concreting works completed. Podium slabs completed and concrete pouring completed upto 1st floor.

  2. MEP second fix works completed upto podium 3.

  3. Painting works in podium 4 in progress.

  4. Project is scheduled to be completed on time.

  5. All Engineering submissions are in progress.

31-08-2025

VIEWZ 2

  1. Ground Floor concreting works completed. Podium slabs completed and concrete pouring completed upto 2nd floor

  2. Painting works in podium 4 completed & podium 5 in progress.

  3. MEP second fix works completed upto podium 3.

  4. Project is scheduled to be completed on time.

Proudly powered by Wpopal.com

Get in Touch

Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.