CONSTRUCTION UPDATES

construction Progress

Web Designer 16.50%
*According to our internal inspection conducted on 30/11/2024, the overall project's progress is 16.50%.

30-11-2024

VIEWZ 1

  1. Fencing work completed.

  2. Shoring works completed.

  3. Piling works completed.

  4. Foundation works in progress.

  5. Soil shifting is in progress.

  6. Capping Beam casting is completed

  7. Dewatering works approved from authorities & works commenced.

  8. All Engineering submissions are in progress.

  9. Main contractor on board.

  10. Project is scheduled to be completed on time.

  11. MEP contractor on board

30-11-2024

VIEWZ 2

  1. Shoring works completed.

  2. Piling works completed.

  3. Excavation works is completed.

  4. Main contractor on board.

  5. Raft works completed & retaining wall completed.

  6. Dewatering works commenced.

  7. All Engineering submissions are in progress.

  8. Project is scheduled to be completed on time.

  9. MEP contractor on board

  10. Ground slab works in progress