construction Progress
Enabling Works in Progress
10.80%
*According to our internal inspection conducted on 31/08/2024, the overall project's progress is 10.80%.
31-08-2024
VIEWZ 1
Fencing work completed.
Shoring works completed.
Piling works under progress.
Foundation works in progress.
Soil shifting is in progress.
Capping Beam casting is completed
Dewatering works approved from authorities & works commenced.
All Engineering submissions are in progress.
Main contractor on board.
Project is scheduled to be completed on time.
31-08-2024
VIEWZ 2
Shoring works completed.
Piling works completed.
Excavation works is completed.
Raft works in progress.
Soil removal works in progress.
Dewatering works commenced.
All Engineering submissions are in progress.
Main contractor on board.
Preparation for blinding & guniting works in progress.
Substructure under progress.
Project is scheduled to be completed on time.