CONSTRUCTION UPDATES

construction Progress

Web Designer 43%
*According to our internal inspection conducted on 31-05-2026, the overall project's progress is 43%.

31-05-2026

VIEWZ 1

  1. Concrete slab casted upto 23rd floor.

  2. MEP works in progress.

  3. Internal block works 19th floor in progress.

  4. Painting works 8th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

31-05-2026

VIEWZ 2

  1. Concrete slab casted upto 23rd floor.

  2. MEP works in progress.

  3. Internal block works 15th floor in progress.

  4. Painting works 7th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

Proudly powered by Wpopal.com

Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.