CONSTRUCTION UPDATES

construction Progress

Web Designer 50%
*According to our internal inspection conducted on 31-07-2026, the overall project's progress is 50%.

31-07-2026

VIEWZ 1

  1. Concrete slab casted upto 30th floor.

  2. MEP works in progress.

  3. Internal block works 24th floor in progress.

  4. Painting works 10th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

31-07-2026

VIEWZ 2

  1. Concrete slab casted upto 30th floor.

  2. MEP works in progress.

  3. Internal block works 24th floor in progress.

  4. Painting works 10th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.