CONSTRUCTION UPDATES

construction Progress

Web Designer 55%
*According to our internal inspection conducted on 31-08-2026, the overall project's progress is 55%.

31-08-2026

VIEWZ 1

  1. Concrete slab casted upto 35th floor.

  2. MEP works in progress.

  3. Internal block works 30th floor in progress.

  4. Painting works 11th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

31-08-2026

VIEWZ 2

  1. Concrete slab casted upto 34th floor.

  2. MEP works in progress.

  3. Internal block works 29th floor in progress.

  4. Painting works 11th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.