Ground Floor concreting works & Podium slabs completed. Concrete pouring completed upto 10th floor.
MEP second fix works completed upto 2nd floor.
Internal block works completed upto 7th floor.
Painting works completed in 2nd floor.
All Engineering submissions are in progress.
DEWA substation approved.