Ground Floor concreting works & Podium slabs completed. Concrete pouring completed upto 4th floor.
MEP second fix works completed upto podium 6.
Internal block works completed upto podium 6.
Painting works until podium 5 in progress.
Project is scheduled to be completed on time.
All Engineering submissions are in progress.
DEWA substation approved.