CONSTRUCTION UPDATES

construction Progress

Web Designer 30%
*According to our internal inspection conducted on 31-07-2025, the overall project's progress is 30%.

31-07-2025

VIEWZ 1

  1. Raft works completed.

  2. Ground Floor concreting works completed. Podium 6 slab completed and amenities floor in progress

  3. All Engineering submissions are in progress.

  4. Project is scheduled to be completed on time.

  5. MEP second fix works in progress at basement and podium.

  6. Painting works in podium 4 in progress.

31-07-2025

VIEWZ 2

  1. Main contractor on board.

  2. Podium 6 slab completed and amenities floor in progress.

  3. All Engineering submissions are in progress.

  4. Project is scheduled to be completed on time.

  5. MEP second fix works started in basement and podium.

  6. Painting works in podium 3 completed & podium 4 in progress.

Proudly powered by Wpopal.com

Get in Touch

Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.