Concrete slab casted upto 15th floor.
MEP works in progress.
Internal block works completed upto 11th floor.
Painting works completed in 4th floor.
All Engineering submissions are in progress.
DEWA substation approved.
Painting works completed in 4rd floor.
Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.