CONSTRUCTION UPDATES

construction Progress

Web Designer 35%
*According to our internal inspection conducted on 31-12-2025 , the overall project's progress is 35%.

31-12-2025

VIEWZ 1

  1. Ground Floor concreting works & Podium slabs completed. Concrete pouring completed upto 10th floor.

  2. MEP second fix works completed upto 2nd floor.

  3. Internal block works completed upto 7th floor.

  4. Painting works completed in 2nd floor.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

31-12-2025

VIEWZ 2

  1. Ground Floor concreting works & Podium slabs completed. Concrete pouring completed upto 10th floor.

  2. MEP second fix works completed upto 2nd floor.

  3. Internal block works completed upto 7th floor.

  4. Painting works completed in 2nd floor.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

Proudly powered by Wpopal.com

Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.