CONSTRUCTION UPDATES

construction Progress

Web Designer 60%
*According to our internal inspection conducted on 30/11/2024, the overall project's progress is 60%.

30-11-2024

  1. Substructure is completed.

  2. Superstructure all slabs casted except roof.

  3. Block works 34th floor in progress.

  4. Plaster works 32nd floor in progress.

  5. Façade works Elevation 1-9th in progress.

  6. Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.

  7. Mock-up apartments works completed in second floor.

  8. MEP items arrived and work in progress.