Substructure is completed.
Superstructure all slabs including roof completed.
Block works 36th floor in progress.
Plaster works 34th & 35th floors in progress.
Façade works Elevation 1-9th in progress.
Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.
Mock-up apartments works completed in second floor.
MEP items arrived and work in progress.