CONSTRUCTION UPDATES

construction Progress

Web Designer 96%
*According to our internal inspection conducted on 31-07-2025, the overall project's progress is 96%.

31-07-2025

  1. Block works completed.

  2. Plaster works completed.

  3. Façade works 36th floor in progress.

  4. Subsequent activities like MEP & Finishing works are in progress in parallel to the structural work.

  5. Mock-up apartments works completed in second floor.

  6. MEP long lead items arrived and installation in progress.

  7. Landscapping works commenced.

  8. Snagging and Desnagging in progress.

  9. DCD inspection in progress.

  10. DEWA permanent power connection in progress.

    Proudly powered by Wpopal.com

    Get in Touch

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.