Mobilization has been completed.
Shoring works has been completed.
Foundation works has been completed.
Excavation works is completed.
Main Contractor on board.
Substructure works are progressing - 60% raft completed & Ground floor slab 50% completed.
First Floor slab works in progress.
Tower crane installed.
MEP contractor on board.
Project is targeted to be completed before time.