Mobilization has been completed.
Shoring works has been completed.
Foundation works has been completed.
Substructure works completed.
Superstructure nearing completion.
MEP second fix & internal partition works in progress.
Project is targeted to be completed before time.
All MEP long lead items oredered and will be received before time.
Final finishing works started