Superstructure completed.
MEP second fix and final fix in progress.
Project is targeted to be completed before time.
All MEP long lead items installed.
Final finishing works & façade works in progress.
Breaching inlet approved.
LV first inspection by DEWA Completed.
DCD inspection in progress
DEWA power permanent power conection in progress.