CONSTRUCTION UPDATES

construction Progress

Web Designer 75%
*According to our internal inspection conducted on 30/11/2024, the overall project's progress is 75%.

30-11-2024

  1. Substructure is completed.

  2. Superstructure completed.

  3. Block works completed.

  4. Plaster works completed.

  5. Façade works 11th-20th Floor in progress.

  6. Podium & Ground Floor works in progress.

  7. MEP final fix & Finishing works are in progress.

  8. Preparation for authority inspection for building completion & service connections in progress.

  9. Breaching inlet approved by DCD.

  10. Structural works in roof completed.

  11. All MEP long lead items recevied and installed.

  12. LV inspection by DEWA done