Substructure is completed.
Superstructure completed.
Block works completed.
Plaster works completed.
Façade works 11th-20th Floor in progress.
Podium & Ground Floor works in progress.
MEP final fix & Finishing works are in progress.
Preparation for authority inspection for building completion & service connections in progress.
Breaching inlet approved by DCD.
Structural works in roof completed.
All MEP long lead items recevied and installed.
LV inspection by DEWA done