CONSTRUCTION UPDATES

construction Progress

10%
*According to our internal inspection conducted on 01/04/2024, the overall project’s progress is
10%.

01-04-2024

  1. Shoring work has been completed.

  2. Shoring assessment test has been completed.

  3. Piling Design under final review with authority.

  4. Excavation in progress.

  5. Main Contractor on board.

  6. Project is targeted to be completed on time.

01-03-2024

  1. Fencing Work Completed - 100%

  2. Project Signboard Completed - 100%

  3. Enabling Contractor appointed & Mobilization started.

  4. 3rd Party for Shoring Verification Appointed.

  5. Dewatering Subcontractor - Appointed.

  6. Dewatering NOC from Nakheel - In Progress.