CONSTRUCTION UPDATES

construction Progress

Web Designer 33%
*According to our internal inspection conducted on 31-03-2026 , the overall project's progress is 33%.

31-03-2026

  1. Slab completion- OCEANZ 1 -upto Level 16 completed, OCEANZ 2 upto Level 10 completed. OCEANZ 3 -Basement 1 completed Ground floor in progress

  2. BLOCK WORK- OCEANZ 1- upto Level 12 in progress. OCEANZ 2 - upto Level 6 in Progress

  3. Plastering - OCEANZ 1 upto Level 7 in Progress, OCEANZ 2 upto Level 2 in progress

  4. Painting work - OCEANZ 1 &2 Basement to Level 3 in progress

  5. MEP 1st FIX OCEANZ 1- upto Level 9 in pogress OCEANZ 2- upto Level 4 in pogress

  6. MEP 2nd FIX Oceanz 1 Level 1-7 in progress, Oceanz 2 Level 2 in progress

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.