Authority approvals obtained and construction activities commenced.
EXCAVATION - completed
Foundation Raft -completed,
Slab completion- OCEANZ 1 -up to Level 43 completed, OCEANZ 2 up to Level 37 completed. OCEANZ 3 -Level 14 completed.
BLOCK WORK- OCEANZ 1- up to Level 36 in progress. OCEANZ 2 - up to Level 27 in Progress, OCEANZ 3 - Level 5 in progress
Plastering - OCEANZ 1 up to Level 24 in Progress, OCEANZ 2 up to Level 23 in progress, OCEANZ 3 - Level 2 in progress
Painting work - OCEANZ 1 Basement to Level 24 in progress, OCEANZ 2 Basement to Level 21 in progress, OCEANZ 3 Basement to Level 2 in progress.
MEP 1st FIX OCEANZ 1- up to Level 37 in progress OCEANZ 2- up to Level 29 in progress OCEANZ 3- up to Level 6 in progress
MEP 2nd FIX Oceanz 1 up to Level 28 in progress, Oceanz 2 Level 24 in progress OCEANZ 3- up to Level 4 in progress
Façade works - OCEANZ 1 - Level 24 in progress, OCEANZ 2 - Level 19 in progress