CONSTRUCTION UPDATES

construction Progress

Web Designer 42%
*According to our internal inspection conducted on 31-07-2026 , the overall project's progress is 42%.

31-07-2026

  1. Authority approvals obtained and construction activities commenced.

  2. EXCAVATION - completed

  3. Foundation Raft -completed,

  4. Slab completion- OCEANZ 1 -upto Level 32 completed, OCEANZ 2 upto Level 25 completed. OCEANZ 3 -Level 2 completed.

  5. BLOCK WORK- OCEANZ 1- upto Level 26 in progress. OCEANZ 2 - upto Level 19 in Progress, OCEANZ 3 - Podium1 in progress

  6. Plastering - OCEANZ 1 upto Level 17 in Progress, OCEANZ 2 upto Level 14 in progress

  7. Painting work - OCEANZ 1 Basement to Level 16 in progress, OCEANZ 2 Basement to Level 12 in progress

  8. MEP 1st FIX OCEANZ 1- upto Level 26 in pogress OCEANZ 2- upto Level 19 in pogress

  9. MEP 2nd FIX Oceanz 1 upto Level 21 in progress, Oceanz 2 Level 16 in progress

  10. Façade works - OCEANZ 1 - Level 11 in progress, OCEANZ 2 - Level 10 in progress