CONSTRUCTION UPDATES

construction Progress

Web Designer 50%
*According to our internal inspection conducted on 31-08-2026 , the overall project's progress is 50%.

31-08-2026

  1. Authority approvals obtained and construction activities commenced.

  2. Excavation - completed.

  3. Foundation raft - completed.

  4. Slab completion - OCEANZ 1 - up to Level 35 completed, OCEANZ 2 - up to Level 28 completed, OCEANZ 3 - Level 5 completed.

  5. Block work - OCEANZ 1 - up to Level 28 in progress, OCEANZ 2 - up to Level 21 in progress, OCEANZ 3 - Podium 2 in progress.

  6. Plastering - OCEANZ 1 - up to Level 19 in progress, OCEANZ 2 - up to Level 17 in progress.

  7. Painting work - OCEANZ 1 - Basement to Level 18 in progress, OCEANZ 2 - Basement to Level 14 in progress, OCEANZ 3 - Basement to Podium 2 in progress.

  8. MEP 1st Fix - OCEANZ 1 - up to Level 29 in progress, OCEANZ 2 - up to Level 22 in progress.

  9. MEP 2nd Fix - OCEANZ 1 - up to Level 25 in progress, OCEANZ 2 - Level 18 in progress.

  10. Façade works - OCEANZ 1 - Level 14 in progress, OCEANZ 2 - Level 10 in progress.