construction Progress

Web Designer 38%
*According to our internal inspection conducted on 30-06-2026 , the overall project's progress is 38%.

30-06-2026

  1. Slab completion- OCEANZ 1 -upto Level 27 completed, OCEANZ 2 upto Level 21 completed. OCEANZ 3 -Podium 6 in progress.

  2. BLOCK WORK- OCEANZ 1- upto Level 21 in progress. OCEANZ 2 - upto Level 17 in Progress, OCEANZ 3 - Podium1 in progress

  3. Plastering - OCEANZ 1 upto Level 14 in Progress, OCEANZ 2 upto Level 12 in progress

  4. Painting work - OCEANZ 1 Basement to Level 14 in progress, OCEANZ 2 Basement to Level 10 in progress

  5. MEP 1st FIX OCEANZ 1- upto Level 21 in pogress OCEANZ 2- upto Level 16 in pogress

  6. MEP 2nd FIX Oceanz 1 upto Level 23 in progress, Oceanz 2 Level 16 in progress

  7. Façade works - OCEANZ 1 - Level 8 in progress, OCEANZ 2 - Level 5 in progress

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.