CONSTRUCTION UPDATES

construction Progress

Web Designer 34%
*According to our internal inspection conducted on 30-4-2026 , the overall project's progress is 34%.

30-04-2026

  1. Slab completion- OCEANZ 1 -upto Level 21 completed, OCEANZ 2 upto Level 15 completed. OCEANZ 3 -Podium 1 & 2 in progress.

  2. BLOCK WORK- OCEANZ 1- upto Level 15 in progress. OCEANZ 2 - upto Level 9 in Progress, OCEANZ 3 - Basement 2 completed

  3. Plastering - OCEANZ 1 upto Level 10 in Progress, OCEANZ 2 upto Level 6 in progress

  4. Painting work - OCEANZ 1 &2 Basement to Level 8 in progress

  5. MEP 1st FIX OCEANZ 1- upto Level 13 in pogress OCEANZ 2- upto Level 7 in pogress

  6. MEP 2nd FIX Oceanz 1 upto Level 13 in progress, Oceanz 2 Level 7 in progress

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.