construction Progress

Web Designer 35%
*According to our internal inspection conducted on 31-05-2026 , the overall project's progress is 35%.

31-05-2026

  1. Slab completion- OCEANZ 1 -upto Level 23 completed, OCEANZ 2 upto Level 19 completed. OCEANZ 3 -Podium 5 in progress.

  2. BLOCK WORK- OCEANZ 1- upto Level 19 in progress. OCEANZ 2 - upto Level 14 in Progress, OCEANZ 3 - Basement 1 in progress

  3. Plastering - OCEANZ 1 upto Level 12 in Progress, OCEANZ 2 upto Level 9 in progress

  4. Painting work - OCEANZ 1 Basement to Level 12 in progress, OCEANZ 2 Basement to Level 7 in progress

  5. MEP 1st FIX OCEANZ 1- upto Level 19 in pogress OCEANZ 2- upto Level 14 in pogress

  6. MEP 2nd FIX Oceanz 1 upto Level 17 in progress, Oceanz 2 Level 9 in progress

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.