Authority approvals obtained and construction activities commenced.
EXCAVATION - completed
Foundation Raft -completed,
Slab Completion – OCEANZ 1: Up to Level 40 completed, OCEANZ 2: Up to Level 33 completed, OCEANZ 3: Level 9 completed.
Block Work – OCEANZ 1: Up to Level 32 in progress, OCEANZ 2: Up to Level 24 in progress, OCEANZ 3: Level 2 in progress.
Plastering – OCEANZ 1: Up to Level 23 in progress, OCEANZ 2: Up to Level 20 in progress.
Painting Work – OCEANZ 1: Basement to Level 22 in progress, OCEANZ 2: Basement to Level 18 in progress, OCEANZ 3: Basement to Level 1 in progress.
MEP 1st Fix – OCEANZ 1: Up to Level 30 in progress, OCEANZ 2: Up to Level 24 in progress, OCEANZ 3: Up to Level 2 in progress.
MEP 2nd Fix – OCEANZ 1: Up to Level 24 in progress, OCEANZ 2: Up to Level 20 in progress, OCEANZ 3: Up to Level 2 in progress.
Façade Works – OCEANZ 1: Level 18 in progress, OCEANZ 2: Level 15 in progress.