CONSTRUCTION UPDATES

construction Progress

Web Designer 55%
*According to our internal inspection conducted on 31-10-2026 , the overall project's progress is 55%.

31-10-2026

  1. Authority approvals obtained and construction activities commenced.

  2. EXCAVATION - completed

  3. Foundation Raft -completed,

  4. Slab completion- OCEANZ 1 -up to Level 43 completed, OCEANZ 2 up to Level 37 completed. OCEANZ 3 -Level 14 completed.

  5. BLOCK WORK- OCEANZ 1- up to Level 36 in progress. OCEANZ 2 - up to Level 27 in Progress, OCEANZ 3 - Level 5 in progress

  6. Plastering - OCEANZ 1 up to Level 24 in Progress, OCEANZ 2 up to Level 23 in progress, OCEANZ 3 - Level 2 in progress

  7. Painting work - OCEANZ 1 Basement to Level 24 in progress, OCEANZ 2 Basement to Level 21 in progress, OCEANZ 3 Basement to Level 2 in progress.

  8. MEP 1st FIX OCEANZ 1- up to Level 37 in progress OCEANZ 2- up to Level 29 in progress OCEANZ 3- up to Level 6 in progress

  9. MEP 2nd FIX Oceanz 1 up to Level 28 in progress, Oceanz 2 Level 24 in progress OCEANZ 3- up to Level 4 in progress

  10. Façade works - OCEANZ 1 - Level 24 in progress, OCEANZ 2 - Level 19 in progress