Mobilization is completed.
Authority approvals obtained and construction activities commenced.
Shoring works completed.
Piling works completed.
Foundation raft comleted.
MEP 1st FIX - Basement 1 in progress
Ground Floor block works in progress.
Slab completion- OCEANZ 1 - podium 3 completed podium 4,5,6 in progress. OCEANZ 2 podium 1 completed, podium 2-4 in progress.