Authority approvals obtained and construction activities commenced.
EXCAVATION - completed
Foundation Raft - OCEANZ 1,2 & 3 completed
Slab completion- OCEANZ 1 - 6 podium and 6 floors completed L7 in progress, OCEANZ 2 - 6 podium & 2 floors completed L3 in progress.
BLOCK WORK- OCEANZ 1&2- upto Level 3 in progress.
Plastering - OCEANZ 1 Basement completed. Upto podium 5 in progress.
Painting work - OCEANZ 1 &2 Basement to podium 6 in progress
MEP 1st FIX (upto Podium 5 -high level in progress)