CONSTRUCTION UPDATES

construction Progress

Web Designer 30%
*According to our internal inspection conducted on 31-12-2025 , the overall project's progress is 30%.

31-12-2025

  1. Authority approvals obtained and construction activities commenced.

  2. EXCAVATION - completed

  3. Foundation Raft - OCEANZ 1,2 & 3 completed

  4. Slab completion- OCEANZ 1 - 6 podium and 6 floors completed L7 in progress, OCEANZ 2 - 6 podium & 2 floors completed L3 in progress.

  5. BLOCK WORK- OCEANZ 1&2- upto Level 3 in progress.

  6. Plastering - OCEANZ 1 Basement completed. Upto podium 5 in progress.

  7. Painting work - OCEANZ 1 &2 Basement to podium 6 in progress

  8. MEP 1st FIX (upto Podium 5 -high level in progress)

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.