CONSTRUCTION UPDATES

construction Progress

Web Designer 38%
*According to our internal inspection conducted on 31-10-2026, the overall project's progress is 38%.

31-10-2026

  1. Main contractor on board.

  2. Substructure works completed.

  3. Superstructure works progressing ahead of schedule

  4. Concrete slab casted on 21st floor.

  5. Block works until 16th floor in progress.

  6. Plaster works until 8th floor on progress

  7. All major subcontractors on board.