CONSTRUCTION UPDATES

construction Progress

Web Designer 33%
*According to our internal inspection conducted on 31-08-2026, the overall project's progress is 33%.

31-08-2026

  1. Main contractor on board.

  2. Substructure works completed.

  3. Superstructure works progressing ahead of schedule

  4. Concrete slab casted on 17th floor.

  5. Block works until 12th floor in progress.

  6. Plaster works until 6th floor in progress

  7. All major subcontractors on board.