CONSTRUCTION UPDATES

construction Progress

97.00%
*According to our internal inspection conducted on 30/09/2024, the overall project's progress is 97.00%.

30-09-2024

  1. Superstructure is completed.

  2. Block and Plaster works completed.

  3. MEP testing & commissioning in progress.

  4. Façade works completed.

  5. Elevator installation works completed.

  6. DCD Approved.

  7. NCC approved & BCC under process.

  8. Snagging in progress.

  9. Project scheduled to be finished before time.

  10. Water Supply & Drainage connected.

  11. Power expected in one week.