CONSTRUCTION UPDATES

construction Progress

75.00%
*According to our internal inspection conducted on 30/04/2024, the overall project's progress is 75.00%.

30-04-2024

  1. All regularities are obtained.

  2. Mobilization is completed.

  3. Shoring is completed.

  4. Piling is completed.

  5. Excavation is completed.

  6. Substructure is completed.

  7. Superstructure is completed.

  8. Block and Plaster works completed upto roof floor.

  9. Subsequent activities like MEP & Finishing works are in progress.

  10. Chillers received and installed at roof.

  11. Façade work is in progress and on schedule.

  12. Elevator installation works completed.

  13. All Long Lead Items are delivered.

  14. Project development in progress.

  15. Project scheduled to be finished on time.

  16. All services connection process with authority started.