CONSTRUCTION UPDATES

construction Progress

Web Designer 45%
*According to our internal inspection conducted on 31-08-2026 , the overall project's progress is 45%.

31-08-2026

  1. Concrete slab casting 22nd floor in progress.

  2. Block works at until 17th floor in progress.

  3. Plaster works at 6th & 7th floor in progress.

  4. Engineering submittals & approvals are in progress.

  5. Internal finishes started.

  6. Substation works completed.