CONSTRUCTION UPDATES

construction Progress

Web Designer 49%
*According to our internal inspection conducted on 31-10-2026 , the overall project's progress is 49%.

31-10-2026

  1. Concrete slab casting 27th floor in progress.

  2. Block works at until 20th floor in progress.

  3. Plaster works until 9th floor in progress.

  4. Engineering submittals & approvals are in progress.

  5. Internal finishes started.

  6. Substation works completed.