CONSTRUCTION UPDATES

construction Progress

11.05%
*According to our internal inspection conducted on 31/08/2024, the overall project's progress is 11.05%.

31-08-2024

  1. Shoring work has been completed.

  2. Piling works completed except for 18 clash piles.

  3. Foundation works in progress.

  4. Excavation works to commence.

  5. Strut works to be finalized.

  6. Main Contractor on board.

  7. Building permit received for the main works.

  8. Construction machineries mobilized.

  9. Engineering submittals & approvals are in progress.

  10. Project is targeted to be completed on time.