CONSTRUCTION UPDATES

construction Progress

Web Designer 47%
*According to our internal inspection conducted on 30-09-2026 , the overall project's progress is 47%.

30-09-2026

  1. Concrete slab casting 24th floor in progress.

  2. Block works at until 18th floor in progress.

  3. Plaster works until 8th floor in progress.

  4. Engineering submittals & approvals are in progress.

  5. Internal finishes started.

  6. Substation works completed.