CONSTRUCTION UPDATES

construction Progress

Web Designer 20%
*According to our internal inspection conducted on 28/02/2025, the overall project's progress is 20%.

28-02-2025

  1. Shoring work has been completed.

  2. Piling works completed.

  3. Main Contractor on board.

  4. Building permit received for the main works.

  5. Raft concrete works completed in Zone 1 & Zone 2. Other zones in progress.

  6. Engineering submittals & approvals are in progress.

  7. Superstructure works commenced.

  8. Project is targeted to be completed on time.

  9. MEP contractor on board and engineering works in progress.