construction Progress

Web Designer 60%
*According to our internal inspection conducted on 31-03-2026, the overall project's progress is 60%.

31-03-2026

  1. Concrete pouring completed upto Roof slab.

  2. Internal blockwork until 37th floor in progress.

  3. Internal finishes until 27th floor in progress.

  4. Façade works in progress

  5. MEP works in progress.

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.