CONSTRUCTION UPDATES

construction Progress

12.00%
*According to our internal inspection conducted on 30/09/2024, the overall project's progress is 12.00%.

30-09-2024

  1. Mobilization completed.

  2. Shoring work has been completed.

  3. Piling works has been completed.

  4. Dewatering works running.

  5. Excavation works under progress

  6. Building Permit has been received.

  7. Main Contractor on board and raft works in progress.

  8. Guniting on shoring under progress.

  9. Project scheduled to be finshed on time.