CONSTRUCTION UPDATES

construction Progress

Web Designer 15%
*According to our internal inspection conducted on 30/11/2024, the overall project's progress is 15%.

30-11-2024

  1. Mobilization has been completed.

  2. Shoring works completed.

  3. Piling works completed.

  4. Foundation works in progress.

  5. Excavation work is in progress.

  6. Main contractor on board & commenced substructure works.

  7. Building permit for the main works received.

  8. Raft works in progress.

  9. Project scheduled to be finished on time.

  10. Construction machineries mobilized.

  11. Engineering submittals & approvals are in progress.

  12. MEP contractor mobilized works at site.