*According to our internal inspection conducted on 31-07-2026 , the overall project's progress is 43%.

31-07-2026

  1. Tower A level 34th floor slab casted & Tower B 15th floor slab casted.

  2. Block works in progress Tower A 23rd Floor & Tower B 5th Floor in progress

  3. Plaster works in progress until 11th floor Tower A & Tower B 1st floor

  4. MEP works in progress.

  5. Engineering submittals & approvals are in progress.

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.