CONSTRUCTION UPDATES

construction Progress

Web Designer 53%
*According to our internal inspection conducted on 31-10-2026 , the overall project's progress is 53%.

31-10-2026

  1. Tower A level 41st floor slab casted & Tower B 27th floor slab casted.

  2. Block works in progress Tower A until 37th Floor & Tower B until 18th Floor in progress

  3. Plaster works in progress until 23rd floor Tower A & Tower B 6th floor

  4. MEP works in progress.

  5. Engineering submittals & approvals are in progress.