CONSTRUCTION UPDATES

construction Progress

Web Designer 48%
*According to our internal inspection conducted on 31-08-2026 , the overall project's progress is 48%.

31-08-2026

  1. Tower A level 38th floor slab casted & Tower B 18th floor slab casted.

  2. Block works in progress Tower A until 28th Floor & Tower B until 9th Floor in progress

  3. Plaster works in progress until 16th floor Tower A & Tower B 3rd floor

  4. MEP works in progress.

  5. Engineering submittals & approvals are in progress.