CONSTRUCTION UPDATES

construction Progress

Web Designer 38%
*According to our internal inspection conducted on 30-06-2026 , the overall project's progress is 38%.

30-06-2026

  1. Tower A level 29th floor slab casting & Tower B 11th floor slab casting completed

  2. Block works in progress Tower A 20th Floor & Tower B 2nd Floor in progress

  3. Plaster works in progress until 6th floor.

  4. MEP works in progress.

  5. Engineering submittals & approvals are in progress.

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.