CONSTRUCTION UPDATES

construction Progress

Web Designer 31%
*According to our internal inspection conducted on 28-02-2026 , the overall project's progress is 31%.

28-02-2026

  1. Concrete slab 12th floor in progress.

  2. Block works in progress at 4th floor.

  3. Plaster works in progress at basement 1.

  4. MEP works in progress.

  5. Engineering submittals & approvals are in progress.

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.