CONSTRUCTION UPDATES

construction Progress

Web Designer 25%
*According to our internal inspection conducted on 31-08-2025, the overall project's progress is 25%.

31-08-2025

  1. Mobilization has been completed.

  2. Shoring & Piling works completed.

  3. Basement 3 concrete completed. Basement 2, 1 7 Ground Floor (85% completed). Podium 1 in progress.

  4. Construction machineries mobilized.

  5. Engineering submittals & approvals are in progress.

  6. MEP works commenced in the basement

  7. Internal finishes commenced.

    Proudly powered by Wpopal.com

    Get in Touch

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.