CONSTRUCTION UPDATES

construction Progress

Web Designer 23%
*According to our internal inspection conducted on 31-07-2026, the overall project's progress is 23%.

31-07-2026

  1. Shoring works completed.

  2. Piling works completed.

  3. Excavation works completed.

  4. Substructure works by Main contractor in progress.

  5. Engineering works & logistics arrangements in progress.