CONSTRUCTION UPDATES

construction Progress

Web Designer 15%
*According to our internal inspection conducted on 30/11/2024, the overall project's progress is 15%.

30-11-2024

  1. Mobilization completed.

  2. Shoring work has been completed.

  3. Piling works has been completed.

  4. Dewatering works running.

  5. Excavation works under progress

  6. Building Permit has been received.

  7. Guniting on shoring under progress.

  8. Main Contractor on board and Ground floor slab works in progress.

  9. Project scheduled to be finshed on time.

  10. MEP subcontractor on board & engineering works in progress.