construction Progress
1.00%
*According to our internal inspection conducted on 30/04/2024, the overall project's progress is 1.00%.
30-04-2024
Fencing work completed.
Shoring Guide wall casting completed.
Shoring Piles casting completed.
Soil shifting is in progress.
Capping Beam casting is in progress.
Dewatering system submitted for authority approval.
All Engineering submissions are in progress.
Piling design approved and expected to start from 15th May 2024.
Main contractor on board.
Project is scheduled to be completed on time.
30-04-2024
Guide Wall completed.
Shoring works completed.
Excavation works of Enabling contractor is completed.
Enabling contractor handed over the site to Main Contractor.
Main pile design submitted and approved by DM.
Piling works started. And in progress
Capping beam completed.
Dewatering system submitted for authority approval.
All Engineering submissions are in progress.
Main contractor on board.
Project is scheduled to be completed on time.