CONSTRUCTION UPDATES

construction Progress

Web Designer 57%
*According to our internal inspection conducted on 30-09-2026, the overall project's progress is 57%.

30-09-2026

VIEWZ 1

  1. Concrete slab casted upto 37th floor.

  2. MEP works in progress.

  3. Internal block works 34th floor in progress.

  4. Painting works 13th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.

30-09-2026

VIEWZ 2

  1. Concrete slab casted upto 36th floor.

  2. MEP works in progress.

  3. Internal block works 32nd floor in progress.

  4. Painting works 13th floor in progress.

  5. All Engineering submissions are in progress.

  6. DEWA substation approved.