Concrete slab casted upto 37th floor.
MEP works in progress.
Internal block works 34th floor in progress.
Painting works 13th floor in progress.
All Engineering submissions are in progress.
DEWA substation approved.
Concrete slab casted upto 36th floor.
Internal block works 32nd floor in progress.