CONSTRUCTION UPDATES

construction Progress

Web Designer 42%
*According to our internal inspection conducted on 31-07-2026 , the overall project's progress is 42%.

31-07-2026

  1. Authority approvals obtained and construction activities commenced.

  2. EXCAVATION - completed

  3. Foundation Raft -completed,

  4. Slab completion- OCEANZ 1 -upto Level 32 completed, OCEANZ 2 upto Level 25 completed. OCEANZ 3 -Level 2 completed.

  5. BLOCK WORK- OCEANZ 1- upto Level 26 in progress. OCEANZ 2 - upto Level 19 in Progress, OCEANZ 3 - Podium1 in progress

  6. Plastering - OCEANZ 1 upto Level 17 in Progress, OCEANZ 2 upto Level 14 in progress

  7. Painting work - OCEANZ 1 Basement to Level 16 in progress, OCEANZ 2 Basement to Level 12 in progress

  8. MEP 1st FIX OCEANZ 1- upto Level 26 in pogress OCEANZ 2- upto Level 19 in pogress

  9. MEP 2nd FIX Oceanz 1 upto Level 21 in progress, Oceanz 2 Level 16 in progress

  10. Façade works - OCEANZ 1 - Level 11 in progress, OCEANZ 2 - Level 10 in progress

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.