CONSTRUCTION UPDATES

construction Progress

Web Designer 38%
*According to our internal inspection conducted on 30-09-2025 , the overall project's progress is 38%.

30-09-2025

  1. Tower 1 - 19th floor slab works in progress. Tower 2 - 12th floor slab works in progress.

  2. MEP second fix works completed until podium 5. Tower 1 floor 8th & 9th in progress. Tower 2 floor 1st & 2nd in progress.

  3. Internal block works completed upto Tower 1 - 14th floor, Tower 2 - 6th floor.

  4. Internal plaster works completed upto Tower 1 - 8th floor, Tower 2 - 2 floor.

  5. Floor tile works completed upto Tower 1 - 3rd floor.

    Proudly powered by Wpopal.com

    Get in Touch

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.