CONSTRUCTION UPDATES

construction Progress

Web Designer 55%
*According to our internal inspection conducted on 28-02-2026, the overall project's progress is 55%.

28-02-2026

  1. Tower 1 & 2 - Roof slab works completed.

  2. Internal block works completed upto Tower 1 - 33rd floor, Tower 2 - 31st floor.

  3. Internal plaster works completed upto Tower 1 - 31st floor, Tower 2 - 25th floor.

  4. Floor tile works completed upto Tower 1 -25th floor, Tower 2 - 16th floor.

  5. Façade works in progress.

    Proudly powered by Wpopal.com

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.