CONSTRUCTION UPDATES

construction Progress

Web Designer 36%
*According to our internal inspection conducted on 31-08-2025, the overall project's progress is 36%.

31-08-2025

  1. Tower 1 - 17th floor slab works in progress. Tower 2 - 9th floor slab works in progress.

  2. MEP second fix works completed until podium 5 & 5th floor works in progress.

  3. Internal block works completed upto Tower 1 - 11th floor, Tower 2 - 2nd floor.

  4. Internal plaster works completed upto Tower 1 - 7th floor, Tower 2 - 1st floor.

  5. Floor tile works completed upto Tower 1 - 1st floor.

    Proudly powered by Wpopal.com

    Get in Touch

    Disclaimer : Danube Properties values your privacy and will use the contact information you provide solely for communicating with you about our products and services. By clicking the submit button, you consent to our sales agents contacting you via phone calls, emails, and WhatsApp messages. You have the right to opt out of these communications at any time. For more details, please review our comprehensive Privacy Policy.

    Real Estate Developer in Dubai
    Follow Us on: