Tower 1 - 17th floor slab works in progress. Tower 2 - 9th floor slab works in progress.
MEP second fix works completed until podium 5 & 5th floor works in progress.
Internal block works completed upto Tower 1 - 11th floor, Tower 2 - 2nd floor.
Internal plaster works completed upto Tower 1 - 7th floor, Tower 2 - 1st floor.
Floor tile works completed upto Tower 1 - 1st floor.