Tower 1 - 27th floor slab works in progress. Tower 2 - 19th floor slab works in progress.
Internal block works completed upto Tower 1 - 24th floor, Tower 2 - 16th floor.
Internal plaster works completed upto Tower 1 - 18th floor, Tower 2 - 15th floor.
Floor tile works completed upto Tower 1 -12th floor, Tower 2 - 2nd floor.
Façade works in progress.