Mobilization completed.
Excavation works in progress.
Main Contractor on board.
Piling works completed for both towers.
MEP contractor on board & engineering works in progress.
Tower 1 Raft completed. GF slab works in progress. Tower 2 foundation works in progress.
Machineries & resources mobilized on site.